Referendum 2016: Construction Update

With the passing of the April 5, 2016 referendum, approximately 70 projects across the district will make our schools safer, more efficient and provide a more capable learning space to prepare children for college, career and the workforce. Thank you for voting!

Here’s an inside look at what’s going on at each of our sites.

MFHS (Click on the photo to navigate the full 360-degree view!)

R0010036[1]

R0010037[1] R0010038[1]

Above are three views of different classrooms in what once was the Tech Ed department. These classrooms will be well equipped to serve students seeking to go into careers in engineering, manufacturing, technology, science, math and art.

R0010039[1]

Above is our main fabrication lab. In the far back you can see the roll up doors that used to house our autos department. In the fall this area will be home to our welders, woodworking, lathes & CNC machines.

To the right of the roll up doors is the doorway to the old woodworking department. This area will now hold our ceramics and some art department classes.

North Middle (Click on the photo to navigate the full 360-degree view!)

R0010022[1]

North’s auditorium hasn’t had an update since it was built approximately 50 years ago, so this refresh is needed! The old seats have been removed and interior demolition will take place over the next two weeks. The footprint of the auditorium isn’t changing, but its look certainly will!

R0010023[1]

R0010024[1]

The other big change over at North Middle School is the addition of the music room off of the auditorium lobby. The structure is finished, and this week they’ll start putting in the electrical system.

R0010025[1]

Shady Lane (Click on the photo to navigate the full 360-degree view!)

R0010031[1]

Shady Lane’s main office/entrance is getting relocated to the center of the parking lot to not only provide safe parking for families that visit the school, but also provide a secured entrance that requires visitors to come directly into the office before entering the school.

Below is the interior, a full roof is getting installed at the end of the week.

R0010032[1]

Just a reminder, here’s a rough schedule of our construction projects, much of which is being completed over the summer:

High School TechEd: Dec. 27, 2016 — Aug. 21, 2017

Shady Lane Main Entrance: Feb. 27, 2017 — Aug. 21, 2017

North Middle Music Room: Feb. 27, 2017 — Aug. 21, 2017

North Middle Auditorium: May 15, 2017 — Oct. 31, 2017

North Middle TechEd: June 12, 2017 — Aug. 21, 2017

North Middle Library: June 12, 2017 — Aug. 21, 2017

High School Library: June 12, 2017 — Aug. 21, 2017

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s